Moving cargo into suitable conditions does not erase an earlier temperature excursion. Exposure duration, logger position and product requirements matter. Preserve records, notify the responsible person and establish whether appropriate pending-review storage is available instead of choosing unloading or rejection by instinct.

Yunxiu · Operations planning reference · Updated 8 November 2026

Check the comparison basis

Review the product's transport or storage requirements, the agreement and measurement units. Vehicle air, package surface and product-core readings are not interchangeable. Verify timestamps, time zone, device identity, location and gaps. Keep the complete record rather than selecting only the period after recovery.

  • Preserve raw data and how it was retrieved.
  • Ask the owner to clarify missing product requirements.

Understand the limits of arrival readings

A normal arrival reading does not prove a normal journey. An abnormal one also needs context about location and method. Use the agreed measurement process and suitable equipment, recording time and position. Obtain approval before opening or contacting a product in a way that could cause contamination or damage.

  • Keep transport history and arrival readings separately.
  • Do not convert an unchecked reading into a quality verdict.

Confirm appropriate pending-review storage

The owner and site should agree whether suitable temporary protection exists, permitted work, continued monitoring and the decision owner. If conditions are unavailable, unloading first is not an adequate plan. Entering a controlled space must not automatically remove the stock hold.

  • Temporary acceptance is not final quality release.
  • Name the owner of testing and response actions.

Close against the responsible quality decision

The authorised product party should decide use, further assessment or another disposition using complete evidence. Record the exact quantity and lot covered by approval. Keep protective actions and uninspected aspects visible. Charges and transport liability can be considered separately; they do not decide product fitness.

  • Retain the link to the original temperature record.
  • Do not extend one approval to unrelated lots.

Before you proceed

  • Correct requirement and measurement basis
  • Complete records preserved
  • Suitable pending storage confirmed
  • Authorised quality decision